• Project Schedule

    Period Deliverables Status
    September 2025 – Finalize detailed project plan, objectives, and scope 

    – Set Up Webpage 
    Done
    October 2025 – Gather digital floor plans, maps, and schematics focusing on freshman areas 

    – Perform site observations to identify navigation challenges, such as abbreviations and facility locations 

    – Abstract data into graph structure for modeling 

    – Set up GitHub repository 
    Done
    November – December 2025 – Frontend Development 

    – Implement presentation layer with ReactJS, Vite, and React Leaflet 

    – Develop UI components for search, filters, and map visualizations. 

    – Backend Development & Initial Integration 

    – Set up Node.js server and MongoDB database. 
    Done
    January 2026 – Integrate frontend with backend APIs. 

    – Implement adapted A* algorithm for pathfinding. 
    Done
    February – March 2026 – Continue App Development 

    – Add features like abbreviation expansion and real-time adjustments. 

    – Conduct unit tests for components. 

    – Fix bugs and refine algorithm elements if necessary. 
    Done
    April 2026 – Prepare finalized implementation, documentation, and demonstrations 

    – Incorporate feedback and make final adjustments. 

    – Conduct usability surveys and evaluations 

    – Design a Project Poster 
    Done